The start dates of most objects are determined automatically as the latest end date of predecessors, before that date it is impossible to begin the work, as there is no readiness to start work. That is why when you create a link, this changes at once the start date of the destination object for the link, or even the schedule of this object is removed at all if the source object is not executed. However, if you want to start work not at the optimum time but later, mark the checkbox "Fix start date" in the tab containing the schedule of the object, it will allow you to enter any start date, which is later than that calculated automatically.
|