Hello Shortki,
I'm currently bulding a project with inshort, and I need to make independant subprocesses Inside a common one. Each starting date have to be independant. To do so, I tried using date triggers for each process. But It seems that the starting date is adjusted to the later one, by creating a late start, so all the subprocesses will finish together. I understand this calculation, but is it possible to create several small processes with independant start and end date, Inside a common process which will take into account the very first start date and the very late date of all of them ? I tried to find the answer in the user guide, but I didn't success.
The idea is explained in the attached file.
Thank you very much for your kind help.