Author Topic: Overdue Report  (Read 4206 times)
Rauschen
Newbie
*

Karma: +1/-0
Posts: 5


View Profile Email
« on: June 10, 2013, 08:54:00 PM »

Hi shortki,

first great app, I like this concept to create projects in a visual way. Im a visual type of guy, so it fits more into my behaivor like other programs.

Im still learning this app, intially I bought it to plan my study, my homeworks and finally my bachalor thesis later this year. however, now I try to use to plan a project at mx work.

Im looking for to create a late task or overdue report and in best way the report should show all task/steps that are overdue (end date < today) and include the impact of successors and the overall project.

Can I run a report for a  project only without showing other?

thx // rauschen
Logged
Rauschen
Newbie
*

Karma: +1/-0
Posts: 5


View Profile Email
« Reply #1 on: June 17, 2013, 12:23:29 PM »

hmmm...no respond?
Logged
shortki
Administrator
Hero Member
*****

Karma: +16/-0
Posts: 566



View Profile Email
« Reply #2 on: June 18, 2013, 01:31:19 PM »

I apologize for the delay in answer, I accidentally missed the topic. It is good that you raised it again.

Now the program can prepare a report about the active tasks having a start date but having no end date. Your condition not quite fits your needs, as a task having a date of completion is already completed. Is it overdue or not, one can understand, only comparing the expected time of completion and the actual one.

The current reporting system is not parametric, so, as now, it is impossible to build a report depending on specific dates or containing calculated fields. However, you can get a CSV file out of the program and build a desired report from it in spreadsheets.

The report is made for the current diagram. If you need a report on a certain project, first open its diagram and then activate the reporting system.
« Last Edit: June 18, 2013, 04:56:02 PM by Argalio » Logged
Rauschen
Newbie
*

Karma: +1/-0
Posts: 5


View Profile Email
« Reply #3 on: August 08, 2013, 04:06:20 PM »

sorry now Im very late.

I think I did not get u 100%. I recordnized the active task report, that will show all active task due in future, present and past. However from project management point of view, I would like to see which task  who are assigned to a resource are overdue to follow up accordingly. which I think it make sense for visibility purpose, not going through all active but not late task, especially for complex project.

ok, there's a work around to import a csv to MSExcel in do the calculation there.

Will u think about to import such reporting feature, or this not part of ur initial concept of app?

thx