Tested on version 3.2.3
When user press "Analyze the diagram as a project" , then inShort turns ON flag "sync plan with reality".
It is a very serious bug.I will explain why it is serious:User has no indication that "sync plan with reality" flag is going to be turned ON!
It has a bad impact on the planned and actual schedule.
Why bad impact?
Because user can not "UNDO" immediately the changes that will be done by "sync plan with reality" flag.
Look,
no project manager in the company/business will use feature that has
direct impact on the planned and actual schedule. I am talking about impact that changes things and can not be "UNDO" immediately.
I don't think that some project manager will sit in the office and will start to shake the ipad in order to "UNDO" inShort BUG

It is not serious.
In the company where I work, each project costs about million of dollars. Of course project managers use expensive project managing applications.
But, these managing applications don't have so cool views ability as your App has: to switch Flow vs Gannt and to planned vs actual results is genius !
The question is - for what type of business projects the below features are already ready for a serious usage ?(1) "Analyze"
(2) "Sync with reality"
In my opinion:The inShort App is ready for business usage without both features.
The "Analyze" and "Sync with reality" are too buggy for the business usage in the current version of inShort (version 3.2.3)
It is only my opinion.
By the way, I understand why in the "Suggestions" section forum, users want to import MS project files to your App!
They want your GUI to view the FLOW CHART of the project, but they prefer to stay with MS application as a project editor.